G98 against G99: the 16 amp line, notify or apply, and what it does to system size
Up to 16 A per phase (about 3.68 kW) you notify after connecting; above it you apply first. What the forms say and how the line shapes inverter size.

Explore this decision
What is your solar array to inverter ratio?
Divide the panel array DC rating by the inverter AC rating to see the DC to AC ratio.
The DC and AC ratings describe different parts of the system.
Explore this decision
Solar inverter clipping calculator: explore power at one moment
Explore a simple instantaneous power limit, not an annual energy-loss forecast.
The entered DC power is available at one instant and the conversion efficiency is constant.
This is a spec-and-sum explainer, not a review. The figures come from the Microgeneration Certification Scheme’s page for installers and from one network operator’s published connection standards, as read on 25 October 2026; where a figure is not on the pages read it is marked “Not stated” rather than filled in. The arithmetic then asks what the line between the two routes does to the size of inverter you can choose, and to the cost of choosing wrongly.
The rule is short and the consequences are not. G98 is for generation up to 16 amps per phase and is a notification after the work. G99 is for anything larger and is an application that must be approved first. The network operator article explains who the operator is and what a refusal looks like; this one sets the two routes against each other and follows the number into inverter and battery choice.
The two routes on one table
| G98 | G99 | Checked | |
|---|---|---|---|
| Threshold | Up to and including 16 A per phase | Above 16 A per phase | 2026-10-25 |
| In kilowatts, single phase | 16 A at 230 V, 3.68 kW | Above 3.68 kW | 2026-10-25 |
| In kilowatts, three phase | 16 A on each of three phases, about 11 kW | Above that | 2026-10-25 |
| Solar PV | Notify with G98 Form B, within 28 days of commissioning | Prior permission, Form A3.1, before connecting | 2026-10-25 |
| Battery | Notify with Form B within 28 days of installation | Over 3.68 kW with storage: Form A1.1 before installation | 2026-10-25 |
| Solar and battery together | Not stated | Fast-track integrated applications use Form A1.2 before installation | 2026-10-25 |
| Equipment | Fully type tested micro-generator | Assessed by the operator | 2026-10-25 |
| Cost to apply | Not stated | Not stated | 2026-10-25 |
The three phase figure is arithmetic on the per-phase rule: 3 times 3.68 kW is 11.04 kW. The MCS page states the limit per phase and the 3.68 kW figure for batteries and storage; it does not itself state an 11 kW figure, and the operator’s own page is the authority for your connection. The kilowatt figure is also the rated output of the inverter, not the size of the panels, which is why so many UK systems pair a larger array with a smaller inverter.
The same MCS page tells installers that some network operators require their own form, so which form your installer submits depends on the operator. The Energy Networks Association, which publishes the engineering recommendations behind G98 and G99, refused automated access on 25 October 2026, so its text was not read directly; the thresholds above are as MCS states them.
Notify after, apply before
The practical difference is who can say no and when. Under G98 the installer connects and then notifies, and the notification’s job is to put the system on the operator’s record. Under G99 the operator assesses whether the local network can take the generation, and can approve it, approve it with conditions, or ask for network work. The installation should not proceed ahead of the answer.
On timing, the honest position is that no operator figure for an ordinary G99 turnaround was found on a primary page. The one published number read is SSEN’s 2026 metered connections guide, which sets guaranteed standards for generation connections: 45 working days for other low voltage connections with low voltage works, with a late payment of £85 per working day, and 65 working days where high voltage works are needed. The same guide says that where a new connection includes G98 type tested micro-generation at a single premises the demand standards apply, that multiple or G99 generation falls under the generation standards, and that for existing connections the standards apply only if a new service connection is required. So that 45 working days is a ceiling for a particular kind of job from a particular operator, not a typical wait for a domestic G99 application, and you should ask your own operator for its current turnaround.
The cost of the wait is not the application. It is that the scaffolding and installer dates should not be fixed until approval is in hand: an installer who promises “installation next week” on a system that needs prior permission has either not applied or not told you.
What the line does to inverter choice
The datasheets show the line in practice. Two inverters read for this site sit exactly on it:
- Solis S6-GR1P3.6K-S: rated output 3.6 kW and rated grid output current 16 A at 230 V; the 4K is 18.2 A and the 5K is 22.7 A (datasheet).
- SolarEdge SE3680H: rated 3,680 VA and 16.0 A maximum continuous output current, with the SE4000H at 18.5 A and the SE5000H at 23.0 A (datasheet).
Both makers’ ranges therefore have a model built to be the largest G98 inverter, and the next size up is a G99 inverter. The Solis article and the SolarEdge article give the other datasheet figures. The SolarEdge datasheet also lists “G98 Type A” and “G98 NI Type A” among its grid standards; the Solis string datasheet lists “G98 or G99”.
A worked household: the same roof, two routes
A south facing roof with room for 5.4 kWp, twelve 450 W panels, at the site model’s 850 kWh per kilowatt, about 4,590 kWh a year.
- Route A: a 3.6 kW inverter, so G98. The array is bigger than the inverter’s rating, 150% of it, which the Solis datasheet recommends as a maximum for the string family. Install when the installer is free, then notify. The cost is clipping on the brightest afternoons, which depends on your roof and is the subject of the clipping article; a figure for it is not stated here, because it varies by orientation and shade.
- Route B: a 5 kW inverter, so G99. Nothing is clipped, but the installation date waits for approval, and the operator may attach an export limit.
The widget below turns panel watts and count into array size so you can set your own roof against the 3.68 kW line.
- 850 kWh per kW a year for a south facing roof (the site model's figure, not a measurement), scaled by the calculator's direction factors shown in the list.
- Pitch and shading are not modelled here. For a roof-specific figure use PVGIS, which is free, or the MCS estimate on the quote.
- Medians are the DESNZ median installed cost per kW, 0 to 4 kW (£1,780) and 4 to 10 kW (£1,697), 2025/26 edition, published 28 May 2026, confirmed against the spreadsheet 2026-10-19. No larger domestic band is published.
- The quote starts at the median for the size shown, so the comparison reads zero until you enter your own total. 440 W per panel is the posts' worked figure; use the wattage on your quote.
Illustrative arithmetic on the inputs shown. For a projection with degradation, replacement and your tariff, use the calculator.
The sum that decides between A and B is the export limit. If a limit curtails 500 kWh a year at the 12p Octopus Outgoing rate, that is £60 a year; 1,500 kWh is £180. On a household that uses a third of its output at home, most of the export is the midday surplus a limit would cut, so ask the installer whether one is expected before choosing B. The larger inverter earns something only when it converts energy a smaller one would clip, which on many roofs is modest.
Batteries move the line
A battery is where households cross the line without noticing. The MCS table puts a battery over 3.68 kW with storage on G99, with its own form before installation, and the existing network operator article adds that a battery that can export counts as generation, so adding one to a system notified under G98 usually needs its own notification or application.
The datasheets read here show why. A 5 kW hybrid inverter is a 5 kW inverter whatever the panels: Solis lists its hybrid in 3, 3.6, 4.6, 5, 6, 8, 9 and 10 kW ratings, and SolarEdge’s Home Hub single phase runs from 2,500 to 10,000 VA. A household adding a 5 kW battery inverter to an existing 3.6 kW solar inverter has 8.6 kW of AC output, not 5, and that aggregate is what the operator counts. Whether a given battery stays under the line depends on its inverter’s rating and on whether it is set to export, so ask the installer which form applies and to state it in writing.
A second household: adding a battery later
A house with 4 kWp of panels behind a 3.6 kW inverter, notified under G98 in an earlier year. It now wants a battery with a 5 kW inverter. On the rules above this is a G99 matter because of the storage, with Form A1.1 before installation, not a quick add-on. The household should ask the installer to confirm the route before the battery is ordered, and what happens to the existing notification. The question of whether the battery earns its price is separate and is on the battery sizing page.
What the quote will say
Grid connection included. 6 kW system, installed within 3 weeks.
Three checks. Which route: a 6 kW inverter is a G99 application, and three weeks is a promise the operator, not the installer, controls. Which inverter rating: “6 kW system” may mean the array or the inverter; the route follows the inverter. And who holds the paperwork: ask for the approval or notification reference in writing, because the operator’s record is what a later battery, extension or export tariff registration will be checked against.
Questions people ask
What is the difference between G98 and G99?
G98 applies up to 16 amps per phase, about 3.68 kW on a single phase supply, and is a notification after commissioning, within 28 days. G99 applies above that and needs permission before connecting. The line measures the inverter’s rated output, not the panels.
How long does a G99 application take?
No typical figure was found on a primary page. The one published standard read is SSEN’s 45 working days for generation connections with low voltage works, which applies in particular cases only. Ask your own operator for its current turnaround and do not book scaffolding before approval.
Can I avoid G99 by fitting a smaller inverter?
Yes, and it is the usual design: a larger array behind an inverter at or below 3.68 kW stays on the notification route, at the price of clipping. It is the rule measuring what it measures, not a loophole, and a battery inverter added later can take the total over the line.
Does a battery need a G99 application?
The MCS table says a battery over 3.68 kW with storage uses Form A1.1 before installation, and a battery at or under the G98 line is notified with Form B within 28 days. The aggregate of every inverter at the property is what counts, so a battery added to an existing system can tip it over.
Check your own numbers
The paperwork decides the route; your roof decides the output and your tariff decides what it is worth. The calculator models the system you describe, including a battery and its replacement, in today’s money. Start from the 6 kWp array with a 5 kWh battery, then reduce the array to see what staying on the notification route costs: open the calculator with the worked example loaded.
Sources
- MCS, Notifying DNOs: G98 up to and including 16 A per phase, notified with Form B within 28 days of commissioning; G99 above that, prior permission with Form A3.1; batteries over 3.68 kW with storage, Form A1.1; solar and battery fast-track, Form A1.2; some operators require their own form. Checked 2026-10-25, mcscertified.com.
- SSEN, Performance standards: metered connections 2026: generation timescales of 45 and 65 working days, £85 per working day late payment, and when the standards apply to G98 and G99. Checked 2026-10-25, ssen.co.uk.
- Ginlong Technologies, Solis S6-GR1P(2.5-6)K-S datasheet: rated output currents 16 A (3.6K), 18.2 A (4K), 22.7 A (5K), recommended maximum PV power 150% of rating. Checked 2026-10-25, solisinverters.com.
- SolarEdge, Home Hub Inverter single phase for Europe datasheet: SE3680H 3,680 VA and 16.0 A, SE4000H 18.5 A, SE5000H 23.0 A, G98 Type A listed. Checked 2026-10-25, portal.segen.co.uk.
- Octopus Energy, Smart Export Guarantee: Outgoing at 12p. Checked 2026-10-25, octopus.energy.
- gowith.solar, What the calculator models, for the 850 kWh per kilowatt figure, what the calculator models.
- The 5.4 kWp roof, the 500 and 1,500 kWh curtailed, the 4 kWp household and the quote box are illustrations, labelled as such. The Energy Networks Association’s pages refused automated access, and no primary figure for a typical G99 turnaround or application fee was found.
Related
- The network operator application, explainedG98 notification against G99 permission, which applies to you, and what a refusal looks like.
- Solar inverters explained: string, hybrid and microWhat the inverter decides, when paying more for one changes the return, and the question that settles which type your roof needs.
- DIY solar in the UK: what you can and cannot do yourselfWhere the regulations draw the line, the plug-in kits that are now legal, and what a self-installed roof costs you in export payments.