The network operator application, explained

G98 notification against G99 permission, which applies to you, and what a refusal looks like.

9 min readreference
Illustration accompanying The network operator application, explained

Connecting a generator to the grid requires telling the network operator. For most domestic solar systems this is a notification after the work is done; for larger ones it is an application for permission beforehand.

Your installer handles it. It is worth understanding anyway, because the route is set by a specific number on your quote, it can add weeks to your timeline, and the answer can cap what you are allowed to export, which changes the savings figure you were quoted.

Who the network operator is

Not your electricity supplier. The distribution network operator owns and runs the cables and substations in your area, and there is exactly one for your region regardless of who you buy electricity from. The industry body Energy Networks Association publishes the connection rules and can point you at which operator covers your postcode.

Switching supplier does not change your network operator.

The two routes, with the actual numbers

G98, notification after connection, applies to installations up to 16 amps per phase, which is 3.68 kilowatts of inverter capacity on a single phase supply. The installer connects the system, then notifies the operator within 28 days, providing the technical details. No waiting, no permission required, and the operator cannot refuse a compliant notification.

G99, application before connection, applies above that threshold. The operator assesses whether the local network can accept the generation, and may approve it, approve it with conditions, or require reinforcement work. The assessment typically takes weeks, occasionally longer in loaded areas, and the installation cannot lawfully proceed ahead of it.

Note what the threshold measures: the inverter’s rating, not the panels’. This is why so many UK systems pair a larger array with a 3.68kW inverter, keeping G98 simplicity at the price of some clipping on the brightest days, and why “which inverter, which route” is really one question.

The two routes on one table

G98G99Checked
Applies toInverter output up to 16 A per phase, 3.68kW on single phaseAnything above that2026-10-19
WhenNotification within 28 days after connectionApplication and approval before connection2026-10-19
Can it be refusedA compliant notification cannot beApproval, conditions, or reinforcement required2026-10-19
TimelineNoneTypically weeks; longer on loaded networks2026-10-19
Export limitNot usualPossible, as a condition2026-10-19
Who does itThe installerThe installer, before scaffolding is booked2026-10-19

Source: the ENA’s connection guidance, as cited across this site; the page blocked automated checking on 19 October 2026, so the thresholds are as previously cited and your installer’s paperwork is the authority for your own connection.

Ask which applies to you

Two questions for your installer, before you sign:

“Does my system require G98 notification or a G99 application, and if G99, is the approval in hand?”

“Do you expect an export limit to be applied?”

The first protects your timeline: a quote promising installation next week for a system that needs prior G99 approval has skipped a step. The second is the one that matters financially.

Export limits, and what they do to your sums

Where the local network is constrained, an operator may permit the installation on condition that export is limited to a certain level, enforced by the inverter.

The system still generates fully. You simply cannot send more than the limit to the grid, so surplus above it is curtailed and lost.

Scale decides the damage. A household consuming most of its generation barely notices: its export rarely reaches the cap. A large array on a low daytime consumption house is the opposite case, because its midday surplus is exactly what the cap cuts, and every curtailed unit was worth the 12p an export tariff pays. A battery softens the blow by absorbing the curtailed peak for evening use, which is worth pricing when a limit is on the table.

A worked limit, in pounds

Take a 6kW array on a house using 3,600 kilowatt hours a year with 40% of it in daylight. At the site model’s 850 kilowatt hours per kilowatt the array makes about 5,100 kWh; the house uses about 1,440 of that directly and exports about 3,660, worth about £439 a year at 12p. Now suppose the operator approves the connection with an export limit that, on this household’s bright-day profile, curtails 500 of those kilowatt hours. The loss is 500 at 12p, about £60 a year, every year, off a saving of about £815; on a projection of twenty five years in today’s money that is about £1,500 the quote did not mention. If the curtailment is 1,500 kilowatt hours, the loss is £180 a year and the array was built to export electricity it cannot sell.

The curtailed volumes are illustrations: how much a given limit actually cuts depends on the shape of your generation and your consumption through the day, which is exactly why the projection should be rerun with the limit applied rather than guessed.

If a limit is expected, ask for the savings projection to be redone with it applied. A projection modelling unrestricted export on a system that will be capped is overstating the return, and the overstatement lands entirely on the export line.

What the quote will say

Grid connection included. Installation available from next week.

“Included” means the installer will do the paperwork, which is normal; what the sentence does not say is which paperwork. For a 3.68kW inverter it is a G98 notification after the job and next week is plausible. For a larger inverter it is a G99 application that must be approved first, and next week is either a promise the installer cannot keep or a sign the application has not been made. Ask which route, whether approval is in hand, and whether a limit is expected, in writing.

Where it gets slower

Delays are usually a function of the area rather than the property. Some networks are heavily loaded, particularly where there has already been a lot of generation connected locally, and assessments take longer.

If you are on a timeline, ask early what the current turnaround is in your area. This is the step most likely to hold up the installation sequence, and it is the one nobody’s scaffolding schedule can hurry.

Batteries count too

A battery that can export to the grid is treated as generation for these purposes, so adding storage to an existing solar system usually requires its own notification or application, and can tip a previously-G98 property over the threshold if the battery inverter adds capacity.

This catches people retrofitting. If your original system was notified without a battery, adding one is a change the operator needs to know about. Your installer should handle it; confirm they have, in writing, because the paperwork trail matters later.

What you should end up with

Keep whatever documentation comes back. You will want it if you later add storage, extend the array, or sell the house, and it is the record of what is permitted at your property.

If an export limit was applied, make sure you know the figure and that the inverter is actually configured to it. A limit agreed on paper and not implemented is a compliance problem sitting in your loft, and one a future export tariff registration can surface at the least convenient time.

Questions people ask

Can I avoid G99 by fitting a smaller inverter?

Yes, and it is the common design: a larger array behind a 3.68kW inverter stays on the G98 notification route, at the cost of clipping on the brightest afternoons. Whether the clipping loss is worth the weeks saved and the smaller inverter’s lower cost is a question with a figure, and the inverter article explains what to ask for. It is not a loophole; it is the rule measuring what it measures.

What does an export limit cost me?

The curtailed kilowatt hours times your export rate. On the worked example, 500 kilowatt hours a year at 12p is about £60, and 1,500 is about £180; the volume depends on how often your surplus exceeds the limit, which a projection with the limit applied can estimate and a guess cannot. A battery that absorbs the curtailed peak for the evening recovers some of it at the import rate instead.

Does the operator ever refuse outright?

Rarely for a domestic application; the usual answers are approval, approval with an export limit, or approval subject to reinforcement work the operator would charge for. Reinforcement is the outcome to ask about early in a heavily loaded area, because it changes the economics entirely and nothing on the quote anticipates it.

Who pays if the network needs reinforcing?

Ask the operator and the installer before proceeding; the position depends on the connection and the operator’s charging arrangements, and this article does not state a figure it cannot source. What is certain is that a reinforcement cost belongs in the projection before you sign, not as a surprise after the G99 answer arrives.

Do not do it yourself

This is one of the reasons a certified installer is worth having. The notification requires technical details of the equipment and the installation, and getting it wrong, or skipping it, causes problems when you later apply for an export tariff: suppliers registering you for the Smart Export Guarantee rely on the installation being certified and properly connected, and a system the network does not know about is a system no supplier will pay. The paperwork is dull precisely because it is load-bearing.

Check your own numbers

The calculator does not apply an export limit, so a capped connection is best judged by rerunning the quote’s projection with the limit; what the calculator shows is how much of the saving sits on the export line in the first place, which is the part a limit can touch. Start from the 6kW example on a low daytime household: open the calculator with the worked example loaded.

Every step from survey to switch-on is collected in buying and installing solar panels.

Sources

  • Energy Networks Association, Connect my generation, the G98 and G99 routes as cited across this site; the page blocked automated checking on 2026-10-19, so the figures are as previously cited, energynetworks.org.
  • Octopus Energy, Smart Export Guarantee: Outgoing at 12p. Checked 2026-10-19, octopus.energy.
  • Ofgem, Smart Export Guarantee, the certification requirement. Checked 2026-10-19, ofgem.gov.uk.
  • gowith.solar, What the calculator models, for the 850 kilowatt hours per kilowatt figure, what the calculator models.
  • The 6kW household and the curtailed volumes are illustrations, labelled as such.